Sinking Garage Deep Soil Stabilization

Project photo: Stabilizing Deep Soil to Prevent a Garage from Breaking Away
Alchatek
Case StudyGeotechnical / Deep Soil Stabilization
garage converted into a bedroom Montana

Stabilizing Deep Soil to Prevent a
Garage from Breaking Away

A property owner in Montana contacted a local geotech contractor about a garage converted into a bedroom that lacked drainage, compacted soil, and a proper footing, and had begun sinking and pulling away from the house.

Job Completion Time
8hours
Product
AP Lift 430
Download as PDF
I · The Problem
Case Study  ·  01
01

What made this job
difficult.

garage converted into a bedroom
Montana

The garage lacked effective rainwater drainage, thoroughly compacted supporting soil, and a proper foundation with a footing like the rest of the house. For these reasons, it had sunk several inches. The 'new bedroom' was beginning to break away from the rest of the house, and the property owner found cracks in the siding and wanted to make sure there would be no further movement.

Key Condition
The garage lacked effective rainwater drainage, thoroughly compacted supporting soil, and a proper foundation with a footing like the rest of the house.
The Constraint
several inches
Sunken
The Goal
The property owner wanted to make sure there would be no further movement.
At a Glance
3ft
Injection Spacing
along the footing of the house
17points
Dual-Tube Injection Points
installed along affected area
8 & 4ft
Injection Depths
at each injection point
30minutes
Cure Time
structural polymer cured in place
II · The Solution
Case Study  ·  02
02

What was specified,
and how it went in.

AP Lift 430

These technicians chose to implement the Deep Lock® process to stabilize the soil at all levels with minimal imposition or downtime to the property owner.

The Material
AP Lift 430
Structural polymer
A multi-use structural polymer ideal for compacting soil, filling voids, and lifting slabs and structures.
The Method
01
Identify
The crew identified the exact parameters of all the unstable soil.
02
Install
Installed a pair of injection tubes every three feet along the footing of the house in the affected area, totaling 17 dual-tube injection points.
03
Inject
Created a high-strength durable polyurethane footer with AP Lift 430, injecting the structural polymer to depths of both eight and four feet at each injection point.
04
Confirm
Performed injections until significant backpressure was reached to confirm full soil compaction.
The Deep Lock® Process
Stabilize the soil at all levels with minimal imposition or downtime to the property owner.
AP Lift 430 was injected at both eight and four feet at each point, creating a high-strength, durable polyurethane footer.
III · The Proof
Case Study  ·  03
03

What the result was,
and what confirmed it.

Cure Time

This highly efficient 'surgical strike' style job was executed by a crew of two within eight hours. No heavy equipment or messy excavation was needed. The structural polymer was cured in place within 30 minutes of injection. Water won't erode it; insects cannot eat or bore into it. The property owner's new bedroom is now sitting on stable soil.

Cure Time
30minutes
The structural polymer was cured in place within 30 minutes of injection.
No Heavy Equipment
A crew of two completed the job within eight hours, with no heavy equipment or messy excavation.
Water won't erode the cured polymer, and insects cannot eat or bore into it.
The Result
The property owner's new bedroom is now sitting on stable soil.
Start the Conversation
Send us the job.
We will send back an approach.

Send us the soil report or the failure photos and Technical Services will return a written approach within two business days.

Alchatek manufactures polyurethane resins, chemical grouts, and injection equipment for infrastructure repair: leak sealing, soil stabilization, concrete lifting, and seawall repair. Headquarters in Tucker, Georgia, with a bonded warehouse in Reno, Nevada.