community pool shell

Cracks in a community pool shell were discharging water into the subgrade. The leak stripped fines from the upper three feet of soil, and the shell settled as bearing was lost beneath it. Patching the cracks alone would not have held, because the soil supporting the pool was still failing.

Key Condition
Penetrometer testing confirmed the loss. The cone advanced through the upper 2.6 feet without a recorded blow, and resistance stayed in single digits down to 3.6 feet. Below that, the profile firmed into competent sandy clay, reaching refusal at 9.5 feet.
The Constraint
3weeks
Design Remedy Duration
The design remedy called for scraping back two feet of subgrade and rebuilding it, a three-week job.
At a Glance
4ft
Injection Grid Spacing
10,000sq ft
Treated Area
900rods
Injection Rods Driven
10ft
Treated Depth
II · The Solution
Case Study  ·  02
02

What was specified,
and how it went in.

AP Lift 475

The contractor specified AP Lift 475 with the Deep Lock® process. The two-component polyurethane expands into weak soil and compacts it in place. Crews injected through rods driven from the surface, leaving the shell and deck undisturbed.

The Material
AP Lift 475
AP Lift 475 with Deep Lock® Process
Two-component polyurethane that expands into weak soil and compacts it in place.
The Method
01
Logged
baseline penetrometer readings to refusal
02
Laid out
a 4-foot injection grid across 10,000 sq. ft. around the pool
03
Drove
900 injection rods and injected AP Lift 475
04
Injected
a second level beneath the shell, compacting the soil between the two injection levels
III · The Proof
Case Study  ·  03
03

What the result was,
and what confirmed it.

Increase in Cumulative Resistance

Restored bearing in the eroded upper three feet, where cumulative blow counts rose from 2 to 101. Increased cumulative resistance 139% through the upper 6.6 feet, with values below that depth unchanged.

Increase in Cumulative Resistance
139%
Increased cumulative resistance 139% through the upper 6.6 feet, with values below that depth unchanged.
Start the Conversation
Send us the job.
We will send back an approach.

Send us the soil report or the failure photos and Technical Services will return a written approach within two business days.

Alchatek manufactures polyurethane resins, chemical grouts, and injection equipment for infrastructure repair: leak sealing, soil stabilization, concrete lifting, and seawall repair. Headquarters in Tucker, Georgia, with a bonded warehouse in Reno, Nevada.