Greenville Gravel Retaining Wall Stabilization

Project photo: Gravel Wall Stabilization
Alchatek
Case StudyGravel Wall Stabilization
brick retaining wall Greenville

Gravel Wall
Stabilization

An old brick retaining wall in downtown Greenville collapsed and crushed three cars, requiring stabilization of the embankment and installation of a new wall system.

AP Fill 720 used
50gallons
Product
AP Fill 720
Download as PDF
I · The Problem
Case Study  ·  01
01

What made this job
difficult.

brick retaining wall
Greenville

There was one area where a portion of the brick wall needed removal, but the temporary concrete retaining wall to protect the property had been poured on a bed of gravel that was being held in place by the remaining brick. The gravel under the temporary wall footing was contained by the remaining brick, which when removed would cause all of the gravel to run out. This section was about 30-35' long, 2' high, and 4-5' deep from the face of the wall to the back.

Key Condition
Removal of the remaining brick would cause the contained gravel to run out from under the temporary wall footing.
The Constraint
30-35ft
length of gravel section
At a Glance
50gallons
AP Fill 720 used
18in
probe spacing
2gallons
polyurethane per probe
5%
catalyst mix
II · The Solution
Case Study  ·  02
02

What was specified,
and how it went in.

AP Fill 720

The contractor selected AP Fill 720 to permeate the gravel and hold it in place while the brick was removed. With the gravel locked in place, the crew was able to install supplemental support jacks under the temporary retaining wall. After the jacks were in place, they were able to install the soil nails followed by the shotcrete.

The Material
AP Fill 720
AP Fill 720
Uncured appearance: brown liquid. Viscosity at 77°F (25°C) (ASTM D4878-98): ± 215 cP (± 215 mPa.s). Density (ASTM D3505-96 [2000]): ± 65.9 lbs/ft³ (± 1.12 kg/dm³).
The Method
01
Space
Injection probes were spaced 18" apart to ensure proper permeation and coverage needed to create one solid mass.
02
Inject
The crew came in at a steep 20 to 30-degree angle behind the brick and put in about 2 gallons of polyurethane per probe, with 5% catalyst mixed in.
03
Supplement
The crew then installed more probes at a shallow 60-degree angle in areas that needed further permeation and coverage, at approximately 2 gallons per probe.
04
Complete
This entire process took one day to complete with a small crew of three people.
Locked in Place
AP Fill 720 permeated the gravel and held it in place while the brick was removed.
With the gravel locked, the crew installed supplemental support jacks under the temporary wall, then the soil nails and shotcrete.
Small Crew
The entire process took one day with a crew of three people.
III · The Proof
Case Study  ·  03
03

What the result was,
and what confirmed it.

to complete grouting

The day after grouting, the site work demolition subcontractor chiseled off the remaining brick from the solidified AP Fill 720 gravel wall - and the project was determined to be a complete success. The entire job was finished quickly with minimal mobilization costs.

to complete grouting
1day
The entire job was finished quickly with minimal mobilization costs.
Why It Started
An old brick retaining wall in downtown Greenville collapsed and crushed three cars.
The embankment had to be stabilized before a new wall system could be installed.
The Day After
The demolition subcontractor chiseled the remaining brick off the solidified AP Fill 720 gravel wall.
Start the Conversation
Send us the job.
We will send back an approach.

Send us the soil report or the failure photos and Technical Services will return a written approach within two business days.