I · The Problem
Case Study  ·  01
01

What made this job
difficult.

loading dock

Lift It Rite was a residential contractor, with 95% of their work in driveways, walkways, and steps. In Spring 2020, they were called to perform a routine $3,500 slab lift beneath a loading dock. Before proceeding, they asked Alchatek for a second look.

Testing with a Dynamic Cone Penetrometer, core soil samples, and a manhole inspection revealed a failing 72” stormwater pipe 25 feet below grade, with deflected joints and progressive soil failure. The scope had shifted from a slab lift to deep soil stabilization and infrastructure repair.

Key Condition
A failing 72” stormwater pipe 25 feet below grade, with deflected joints and progressive soil failure.
The Constraint
72in
Failing stormwater pipe
25 feet below grade
At a Glance
72in
Stormwater pipe diameter
25ft
Depth below grade
1month
Completion time
II · The Solution
Case Study  ·  02
02

What was specified,
and how it went in.

AP700 and AP475

Instead of selling foam, Lift It Rite presented an engineered solution: chemical grout injection, deep stabilization with AP700, and void fill and lift with AP475. The facility remained operational. They competed against full pipe replacement. They won.

The Material
AP700 and AP475
AP700 & AP475
AP700 used for deep stabilization; AP475 used for void fill and lift.
The Method
01
Tested
Tested the soil with a Dynamic Cone Penetrometer.
02
Collected
Collected core soil samples.
03
Inspected
Inspected a nearby manhole to investigate potential water leak issues.
04
Presented
Presented an engineered solution using chemical grout injection, AP700, and AP475 instead of a standard slab lift.
III · The Proof
Case Study  ·  03
03

What the result was,
and what confirmed it.

Project Value
Spring 2020

Completed in about one month, the project was worth six months of normal residential revenue, comparable to Lift It Rite's entire first year in business.

They moved from residential slab lifting to commercial infrastructure stabilization, diagnosing root cause before prescribing solutions and gaining the confidence to bid deeper commercial scopes. The job opened a new revenue category for the company.

Project Value
$377,000
Completed in ~1 month; equal to 6 months of normal residential revenue; comparable to their entire first year in business.
Start the Conversation
Send us the job.
We will send back an approach.

Send us the soil report or the failure photos and Technical Services will return a written approach within two business days.

Alchatek manufactures polyurethane resins, chemical grouts, and injection equipment for infrastructure repair: leak sealing, soil stabilization, concrete lifting, and seawall repair. Headquarters in Tucker, Georgia, with a bonded warehouse in Reno, Nevada.